The new library building will be constructed at the Main Street property where the current library stands. This property was deeded as a gift to the City of Athena in 1958 by the Vernita Watts Adams and Foster family estates for use in perpetuity as a library site. Additional land has been donated by Bill Ezell of Ezell Construction. In February 2006, based on preliminary architectural and technical assessments, the project budget was designated at $760,590. In OCtober of 2006, based on additional research, more detailed design development, increases in material costs, and current building cost indices for the northeastern Oregon area, the ALFA board revised the project budget to $864,469 in October 2006.
ACCOMPLISHMENTS TO DATE:
LIBRARY NEEDS:
Public meetings and work sessions throughout have determined that the following are critical components for the new facility in the view of community members and leaders:
PROJECT TIMELINE
| February 2006 | Final report by architectural consultant team at Feb. 21st ALFA annual meeting. Annual ALFA membership drive. |
| Feb-March 2006 | Final process elements in place with City Council for architect/contractor procedures, building oversight process, and committee. City Council Resolution passed. |
| Feb-Dec. 2006 | Grant writing, donation solicitations, and special fundraising events continue |
| April–May 2006 | RFP advertising and packet distribution to architectural firms. |
| June-July 2006 | Architect selection: Fred C. Gast, Jr., FAIA |
| August 2006 | Architect contract signed; contract reviews pro bono by attorney Sam Tucker |
| June-Oct. 2006 | Architectural planning, budget fine-tuning, artwork solicitations. Continuation of furnishings and fixtures research. |
| Sept-Dec. 2006 | Work sessions and completion of design development. Initiate construction drawings. |
| December 2006 | Achievement of capital campaign fund-raising proportions, i.e., minimum of 30% local and a maximum of 70% from external philanthropy. |
| Jan. 2007-Feb. 2007 | Final construction drawings/plans readied. City Planning Commission, City Council, and State Building Office submissions/presentations. Evaluation of financial status. Construction phase planning. SOQs from contractor/cosntruction firms. Pre-bid conference. RFPs and selection of contractor. |
| February-March 2007 | ALFA Annual Meeting and report to the membership. Permits, specifications, construction material orders final. |
| Feb.-Sept. 2007 | Follow-up grant proposals and fundraisers to fulfill any financing gaps. |
| April 2007 | Transfer library to temporary quarters . |
| June-July 2007 | Demolition and site preparation/development; ground-breaking. |
| June-August 2007 | Finalization of interior furnishings orders to ensure timely deliveries; public artwork designed and commissioned. |
| Jan-Feb 2008 | Grand opening of new Athena library. |